Monday January 25, 2016
Today we began work at Olochani to put in a concrete floor. The first step was getting to the site. We can't drive there so we carried what we needed up the hill, a walk of about 1 km. I know it doesn't look particularly steep from the camera's viewpoint, but it is. The trees you see in the far distance are fairly close to the summit.
![]()
Frank had to help push the piki piki up the hill. Unfortunately I don't have an extra camera man or you would have seen me lugging some of the rest of the boards up the hill.
![]()
Since the first order of business was to excavate for the slab, Frank took the opportunity to rest a bit as there were not enough jembes to go around.
![]()
![]()
However as soon as that was done, it was time to begin the foundation fill.
![]()
![]()
While the crew was busy on the floor, the carpenter was working on building doors for the new latrine outside.
![]()
![]()
![]()
![]()
Trimming the door with a panga.
![]()
Meanwhile, the pundas (donkeys) were bringing the water for the project.
![]()
The water is stored in bigger containers on site. The way it looks, those donkeys are going to get a workout bringing water up the hill.
![]()
The cement cart arrived, pulled by a tractor and the bags were offloaded to be used tomorrow.
![]()
Tomorrow we'll start pouring the floor and Wednesday we'll do the finish coat.
When you subscribe to the blog, we will send you an e-mail when there are new updates on the site so you wouldn't miss them.